Monday, 19 October 2009

7th October 2009

The second pair of piles that support the top of the access ramp were pushed in and driven to a set today; then the barge was moved ready to drive the piles that support the access ramp halfway down. I was relieved that the larger piles are going in to roughly the same depth as the smaller piles that support the veranda, however they aren't going in the to depth specified for the pontoon piles which is a bit of a worry.