Monday, 13 September 2010

19th February 2010

The first half of the Galvanised rail for the edge of the veranda was delivered on the 5th Feb, today the second half of the rail arrived from the galvanisers and is carried round to the club and stacked on the veranda ready for installation. I'm starting to get a bit anxious about time as the season is to start in Mid march ; the handrail is to be bolted down before the glass people will measure for the glass as they are worried that the railing may distort when bolted down. (I doubt it, I've seen how massive the railing is). The glass will take over a week to be made as it has to be sent to London to be toughened.