Thursday, 18 February 2010

19th January 2010

The working party starts on the deck. In order to speed progress we have arranged for small teams to work on the Thursday and Friday mornings. The original plan was to start at the down river end of the veranda and work steadily up the deck. However, with the number of people that we have it is decided to have 3 gangs, each starting at different points on the deck so work can proceed at three time the pace. Some careful measuring is done to make sure that the start points for those who start in the middle of the deck fall on a multiple of the width of the deck board plus gap.