Friday, 20 November 2009

30th October 2009

By this afternoon the three piles that locate the landing platform were in place. The good news is that they all went 4metres into the mud with the top of the tubular splice just level with the mud as intended. Today is the last day when we were permitted to pile, however thereare still 2 piles to be driven. The Environment agency had said that they would be flexible if we didn't quite finish so we will be able to complete the last 2 piles next week.